Kansas · data as of 1 Nov 2026
Kansas: 54 MW of existing data centers. 500–1,000 MW in the pipeline.
12 projects tracked from county filings, state records and news. Status and permit facts link to their sources.
We haven't yet searched Kansas for data center projects beyond the ones we track here.
Projects by stage
| Stage | Projects | MW |
|---|---|---|
| Land & zoning | 1 project | not reported |
| Under construction | 2 projects | 500–1,000 MW |
| Operating | 9 projects | 54 MW |
| Total | 12 projects | 974+ MW |
+ = at least. MW includes Grounded Compute research (Q2 2026) where no public source gives a value.
Where the pipeline is
Counties shaded by MW
12 of 12 projects mapped · locations from our project list · as of 1 Nov 2026
County shading
- Under 500 MW
- 500–2,000 MW
- 2,000+ MW
Data center projects
- Planned
- Permitted
- Under construction
- Operating
- Withdrawn
Pin size: MW
Counties with the most MW
+ = at least
- Johnson974+ MW
12 projects
Moratoriums
As of 31 Oct 2026, we count at least 20 local data center pauses in force in Kansas, no bans and 14 proposals, across its counties, cities and townships. At state level, a bill or proposal is pending.
Kansas moratorium tracker: every row with its sourceCounties with a project (1)
Counties with 3 or more projects have their own page
| County | Projects | Under construction or operating | MW |
|---|---|---|---|
| Johnson County | 12 | 11 | 974+ MW |
| 1 counties | 12 | 11 | Calculated |
Projects
5 projects named free · 7 more in the Kansas file
| Developer · address | County | Stage | MW range | Dates | ID |
|---|---|---|---|---|---|
| DataBank · 10605 W 84th Terrace, Lenexa | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0001 |
| DataBank · 15721 College Boulevard, Lenexa | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0002 |
| QTS · 12851 Foster Street, Overland Park | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0003 |
| TierPoint · 14500 W. 105th Street, Lenexa | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0004 |
| LightEdge · 17501 W. 98th Street Pillar #18-33, Lenexa | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0005 |
| Developer and address: in the paid file | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0006 |
| Developer and address: in the paid file | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0007 |
| Developer and address: in the paid file | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0008 |
| Developer and address: in the paid file | Johnson County | Operating | under 100 MW | First recorded 25 Oct 2026 | KS-JOH-0009 |
| Developer and address: in the paid file | Johnson County | Under construction | 500–1,000 MW | Last change 1 Nov 2026 | KS-JOH-0011 |
| Developer and address: in the paid file | Johnson County | Under construction | 100–500 MW | Last change 1 Nov 2026 | KS-JOH-0012 |
| Developer and address: in the paid file | Johnson County | Land & zoning | MW not reported | Last change 1 Nov 2026 | KS-JOH-0010 |
7 more projects: names, developers and sources in the Kansas file →
FAQ
- How many data centers are under construction in Kansas?
- 2 of 12, as of 1 Nov 2026. 9 more operating.
- How much data center capacity is in Kansas's pipeline?
- 500–1,000 MW in the pipeline (500–1,000 MW under construction, not reported planned), and 54 MW operating. These are floors: where no public source gives a MW value, the total uses Grounded Compute research (Q2 2026).
- Which Kansas county has the most data center projects?
- Johnson County: 12 projects.
Cite this page
Source: Grounded Compute, Kansas data centers, 1 Nov 2026. https://groundedcompute.com/us/kansas
The Kansas file: every tracked project, with its sources
- Kansas file: every project named, with developer and address
- MW, and source links on status and permit fields
- Excel workbook + CSV, refreshed monthly
Data centers in other states
Nearby
- Colorado (43 projects, 1.5+ GW)
- Missouri (34 projects, 7.0+ GW)
- Oklahoma (23 projects, 5.3 GW)
- Nebraska (15 projects, 1.8 GW)
Largest