Mississippi · data as of 1 Nov 2026
Mississippi: 1.4 GW of existing data centers. 4.3 GW in the pipeline.
10 projects tracked from county filings, state records and news. Status and permit facts link to their sources.
We haven't yet searched Mississippi for data center projects beyond the ones we track here.
Projects by stage
| Stage | Projects | MW |
|---|---|---|
| Land & zoning | 1 project | 500–1,000 MW |
| Power secured | 1 project | 500–1,000 MW |
| Under construction | 4 projects | 3.0 GW |
| Operating | 4 projects | 1.4 GW |
| Total | 10 projects | 5.7 GW |
+ = at least. MW includes Grounded Compute research (Q2 2026) where no public source gives a value.
Where the pipeline is
Counties shaded by MW
10 of 10 projects mapped · locations from our project list · as of 1 Nov 2026
County shading
- Under 500 MW
- 500–2,000 MW
- 2,000+ MW
Data center projects
- Planned
- Permitted
- Under construction
- Operating
- Withdrawn
Pin size: MW
Counties with the most MW
+ = at least
- Madison2.2 GW
3 projects - Lauderdale1,000+ MW
2 projects - DeSoto500–1,000 MW
1 project - Hinds100–500 MW
1 project - Oktibbehaunder 100 MW
1 project - Rankin1,000+ MW
1 project - Warren500–1,000 MW
1 project
Moratoriums
As of 31 Oct 2026, we count at least 3 local data center pauses in force in Mississippi, no bans and 1 proposal, across its counties and cities. At state level: checked, nothing found.
Mississippi moratorium tracker: every row with its sourceCounties with a project (7)
Counties with 3 or more projects have their own page
| County | Projects | Under construction or operating | MW |
|---|---|---|---|
| Madison County | 3 | 3 | 2.2 GW |
| Lauderdale County | 2 | 1 | 1,000+ MW |
| DeSoto County | 1 | 1 | 500–1,000 MW |
| Hinds County | 1 | 1 | 100–500 MW |
| Oktibbeha County | 1 | 1 | under 100 MW |
| Rankin County | 1 | 1 | 1,000+ MW |
| Warren County | 1 | 0 | 500–1,000 MW |
| 7 counties | 10 | 8 | Calculated |
Projects
5 projects named free · 5 more in the Mississippi file
| Developer · address | County | Stage | MW range | Dates | ID |
|---|---|---|---|---|---|
| AWS · 1001 Industrial Park Drive, Clinton | Hinds County | Operating | 100–500 MW | Last change 1 Nov 2026 | MS-HIN-0001 |
| AWS · Nissan Parkway, Canton | Madison County | Operating | 100–500 MW | Last change 1 Nov 2026 | MS-MAD-0001 |
| AWS · Madison County Parkway, Canton | Madison County | Operating | 1,000+ MW | Last change 1 Nov 2026 | MS-MAD-0003 |
| C Spire · 401 Research Boulevard, Starkville | Oktibbeha County | Operating | under 100 MW | First recorded 25 Oct 2026 | MS-OKT-0001 |
| AVAIO Digital · Highway 18 & East Metro Access Road, Brandon | Rankin County | Under construction | 1,000+ MW | Last change 1 Nov 2026 | MS-RAN-0001 |
| Developer and address: in the paid file | DeSoto County | Under construction | 500–1,000 MW | Last change 1 Nov 2026 | MS-DES-0001 |
| Developer and address: in the paid file | Lauderdale County | Under construction | 500–1,000 MW | Last change 1 Nov 2026 | MS-LAU-0001 |
| Developer and address: in the paid file | Madison County | Under construction | 500–1,000 MW | Last change 1 Nov 2026 | MS-MAD-0002 |
| Developer and address: in the paid file | Warren County | Power secured | 500–1,000 MW | Last change 1 Nov 2026 | MS-WAR-0001 |
| Developer and address: in the paid file | Lauderdale County | Land & zoning | 500–1,000 MW | Last change 1 Nov 2026 | MS-LAU-0002 |
5 more projects: names, developers and sources in the Mississippi file →
FAQ
- How many data centers are under construction in Mississippi?
- 4 of 10, as of 1 Nov 2026. 4 more operating.
- How much data center capacity is in Mississippi's pipeline?
- 4.3 GW in the pipeline (3.0 GW under construction, 1,000+ MW planned), and 1.4 GW operating. These are floors: where no public source gives a MW value, the total uses Grounded Compute research (Q2 2026).
- Which Mississippi county has the most data center projects?
- Madison County: 3 projects.
Cite this page
Source: Grounded Compute, Mississippi data centers, 1 Nov 2026. https://groundedcompute.com/us/mississippi
The Mississippi file: every tracked project, with its sources
- Mississippi file: every project named, with developer and address
- MW, and source links on status and permit fields
- Excel workbook + CSV, refreshed monthly
Data centers in other states
Nearby
- Tennessee (27 projects, 2.3+ GW)
- Alabama (21 projects, 3.4+ GW)
- Louisiana (14 projects, 7.2+ GW)
- Arkansas (7 projects, 3.2 GW)
Largest