Collin County, TX: 404+ MW of existing data centers. 377+ MW in the pipeline.
- As of 1 Nov 2026
- 26 projects: 1 announced, 4 land & zoning, 2 under construction, 19 operating
We haven't yet searched Texas for data center projects beyond the ones we track here.
At a glance · Calculated
Operating
404+ MW
19 projects
Under construction
100–500 MW
2 projects
Planned
275+ MW
5 projects
Proposed projects; not all will be built.
Source: Grounded Compute, Collin County TX data centers, 1 Nov 2026. https://groundedcompute.com/us/texas/collin-county
Map · Collin County
26 of 26 projects mapped · locations from our project list · as of 1 Nov 2026
County shading
- Under 500 MW
- 500–2,000 MW
- 2,000+ MW
Data center projects
- Planned
- Permitted
- Under construction
- Operating
- Withdrawn
Pin size: MW
MW: Collin and its neighbours
Projects (26)
| Developer · address | Stage | MW range | Dates | ID |
|---|---|---|---|---|
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0001 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0002 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0003 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0005 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0006 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0007 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0008 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0009 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0010 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0011 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0012 |
| Developer and address: in the paid file | Operating | MW not reported | First recorded 25 Oct 2026 | TX-CLN-0013 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0014 |
| Developer and address: in the paid file | Operating | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0015 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0016 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0017 |
| Developer and address: in the paid file | Operating | MW not reported | First recorded 25 Oct 2026 | TX-CLN-0018 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | TX-CLN-0020 |
| Developer and address: in the paid file | Operating | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0021 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0023 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0024 |
| Developer and address: in the paid file | Land & zoning | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0004 |
| Developer and address: in the paid file | Land & zoning | MW not reported | Last change 31 Oct 2026 | TX-CLN-0019 |
| Developer and address: in the paid file | Land & zoning | 100–500 MW | Last change 31 Oct 2026 | TX-CLN-0022 |
| Developer and address: in the paid file | Land & zoning | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0025 |
| Developer and address: in the paid file | Announced | under 100 MW | Last change 31 Oct 2026 | TX-CLN-0026 |
26 more projects: names, developers and sources in the Texas file →
The Texas file: every tracked project, with its sources
Our moratorium tracker and market tracker are free. Project-level information is an annual subscription.
- Texas file: every project named, with developer and address
- MW, and source links on status and permit fields
- Excel workbook + CSV, refreshed monthly