Licking County, OH: 2.9+ GW of existing data centers. 6.5+ GW in the pipeline.
- As of 1 Nov 2026
- 46 projects: 3 announced, 5 land & zoning, 18 under construction, 20 operating
We haven't yet searched Ohio for data center projects beyond the ones we track here.
At a glance · Calculated
Operating
2.9+ GW
20 projects
Under construction
3.5+ GW
18 projects
Planned
3.0 GW
8 projects
Proposed projects; not all will be built.
Source: Grounded Compute, Licking County OH data centers, 1 Nov 2026. https://groundedcompute.com/us/ohio/licking-county
Map · Licking County
46 of 46 projects mapped · locations from our project list · as of 1 Nov 2026
County shading
- Under 500 MW
- 500–2,000 MW
- 2,000+ MW
Data center projects
- Planned
- Permitted
- Under construction
- Operating
- Withdrawn
Pin size: MW
MW: Licking and its neighbours
Projects (46)
| Developer · address | Stage | MW range | Dates | ID |
|---|---|---|---|---|
| Meta · Miller Road, New Albany | Operating | 1,000+ MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0029 |
| Meta · 4407 Clover Valley Road, New Albany | Operating | 1,000+ MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0036 |
| Meta · 3439 Clover Valley Road, New Albany | Operating | 1,000+ MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0040 |
| Google · 1101 Beech Road SW, New Albany | Operating | 500–1,000 MW | First recorded 25 Oct 2026 | OH-LIC-0046 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0003 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0004 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0017 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0018 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0019 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0020 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0022 |
| Developer and address: in the paid file | Operating | 100–500 MW | First recorded 25 Oct 2026 | OH-LIC-0023 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0024 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0025 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0026 |
| Developer and address: in the paid file | Operating | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0031 |
| Developer and address: in the paid file | Operating | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0032 |
| Developer and address: in the paid file | Operating | under 100 MW | First recorded 25 Oct 2026 | OH-LIC-0033 |
| Developer and address: in the paid file | Operating | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0034 |
| Developer and address: in the paid file | Operating | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0037 |
| Developer and address: in the paid file | Under construction | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0001 |
| Developer and address: in the paid file | Under construction | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0002 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | OH-LIC-0007 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | OH-LIC-0008 |
| Developer and address: in the paid file | Under construction | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0009 |
| Developer and address: in the paid file | Under construction | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0010 |
| Developer and address: in the paid file | Under construction | 500–1,000 MW | Last change 31 Oct 2026 | OH-LIC-0011 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | OH-LIC-0012 |
| Developer and address: in the paid file | Under construction | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0014 |
| Developer and address: in the paid file | Under construction | 500–1,000 MW | Last change 31 Oct 2026 | OH-LIC-0021 |
| Developer and address: in the paid file | Under construction | 500–1,000 MW | Last change 31 Oct 2026 | OH-LIC-0027 |
| Developer and address: in the paid file | Under construction | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0030 |
| Developer and address: in the paid file | Under construction | 1,000+ MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0035 |
| Developer and address: in the paid file | Under construction | 100–500 MWCampus total, counted once | Last change 31 Oct 2026 | OH-LIC-0039 |
| Developer and address: in the paid file | Under construction | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0041 |
| Developer and address: in the paid file | Under construction | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0042 |
| Developer and address: in the paid file | Under construction | under 100 MW | Last change 31 Oct 2026 | OH-LIC-0043 |
| Developer and address: in the paid file | Under construction | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0044 |
| Developer and address: in the paid file | Land & zoning | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0005 |
| Developer and address: in the paid file | Land & zoning | 500–1,000 MW | Last change 31 Oct 2026 | OH-LIC-0013 |
| Developer and address: in the paid file | Land & zoning | 500–1,000 MW | Last change 31 Oct 2026 | OH-LIC-0016 |
| Developer and address: in the paid file | Land & zoning | under 100 MW | Last change 31 Oct 2026 | OH-LIC-0028 |
| Developer and address: in the paid file | Land & zoning | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0045 |
| Developer and address: in the paid file | Announced | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0006 |
| Developer and address: in the paid file | Announced | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0015 |
| Developer and address: in the paid file | Announced | 100–500 MW | Last change 31 Oct 2026 | OH-LIC-0038 |
42 more projects: names, developers and sources in the Ohio file →
The Ohio file: every tracked project, with its sources
Our moratorium tracker and market tracker are free. Project-level information is an annual subscription.
- Ohio file: every project named, with developer and address
- MW, and source links on status and permit fields
- Excel workbook + CSV, refreshed monthly